Install Fujitsu 2-ton ductless heating and cooling system for server room. Remove and dispose of existing ductless system.
Work at this address
20 Jesup Rd
Westport, Connecticut · Parcel C09130000
39 matched work records at this property, plus documented work nearby.
Work at this address
Recorded work history
39 matched records.
Replace one dual car charger.
Add process cooling to handle increased heat load from computer equipment in room 131 and room 205. Add 1.5 ductless split in room 131 to handle increased sensible heat load. Add 2-ton ductless split to room 205 to handle increased sensible heat load.
Install temp tent 1 20-by-40-foot frame tent over patio. No lighting. To include fire exit, wind meter, bull horn. Library exits shall be clear. Tent company to monitor wind speed at all times. Event date 6-12-21.
Pour foundation for a piece of artwork.
New annex building in parking lot for book storage.
Provide a feed, 3-phase, 4-wire, to the new annex building located in the parking lot for book storage.
Replace existing temperature controls, install new controllers for new HVAC equipment, install thermostats, and disconnect and reconnect electrical feeds to HVAC equipment being replaced.
See sub-permits: police station, also known as 50 Jesup.
Replace 12 split systems and air conditioners, and replace the MUA unit and fan for the gun range.
Installation of 6 tents: 20' x 30', 30' x 60', 20' x 20'; 60' x 150; 30' x 40'; 20' x 30' for 7/20/19 - 7/23/19 event. Set up 7/12/19. Tent company to monitor wind.
Rooftop solar array: flush mounted. System size: 39.420 kW dc, 36.000 kW AC. Module qty. And type: 108 nsp d6m365h4a. Inverter qty. And type: 1 solectria pvi 36tl.
Installation of 39.420 kW solar array. Chris marseglia pe to sign off on installation. Steve gendrrau pe to sign off on electrical.
Renovate lockers, also known as 50 Jesup Road.
Rewire the men's and women's locker rooms inside the police department.
Modifications to the fire alarm system for the men's and women's locker area.
Renovate the men's and women's locker rooms, install new fixtures, and relocate the slop sink.
Install 60' x 80', 20' x 20', 6' x 10' for 8/25/18 event.
Install 2 tents, 30' x 60' and 60' x 150' for july 14-17 event. Tent company to monitor wind.
60-by-150-foot Epic pole tent. Event 4-21-18. Remove on 4-23-18. Tent company to monitor wind load.
See sub-permits.
Run 4 new 3/4" conduit for above ground tank.
Library: Complete interior renovation to all 3 floors of the existing building (construction to be phased). Construct a new main entry with patio and stairs to grade. Under special inspections.
Supply and install generator, dist. Equip. Lighting, receptacles, wire alarm system, black bow, conduit, tel/data, HVAC, landscape lighting, relocate existing lighting, supply and install new lighting controls.
Furnish and install boilers, piping, pipe insulation, water source heat pumps, heat exchangers, VAV's and fpb's, exhaust fans, unit heaters, erv, snow melt system, cooling water, split AC's, sound attenuators, fin tube radiation, duct rgd's, balancing and cont.
Wire VAV's, t-states, 24 volts comm conduit, and j-hooks.
Low-voltage wiring and equipment for a security system, card access system, and video system.
Plumbing related to library renovation.
Tele data and cabling installation.
Install sprinkler system.
CRS# 3096801: Provide new 800 amp equipment and service conductors for a new fire pump. New fire service disconnect switch and CT cabinet. New service conductors and feeders for the fire pump.
6 tents on jesup green with power, 60-by-150-foot' 30-by-60-foot', 30-by-40-foot', 20-by-40-foot', 20-by-30-foot', 20-by-20-foot' - power by temp. Lines from library, ext. Outlets. Tent company to monitor wind speed. Event july 15-18.
Install one 120-gallon propane tank with a fuel line run and connected to the generator.
See sub-permits: generator.
Install a 20 kW auto standby generator to power emergency lighting.
Install 60' x 150' and 9' x 10' tents on Jesup Green for Maker Fair on 4/22/17. All power from a generator. Plug-in connections. Wind loading to be monitored by the tent company.
See sub-permits for the EV charging station at Westport Library.
Install 1 dual-mount pedestal EV charging station.
Install 60-by-150-foot, 50-by-60-foot, 30-by-40-foot and 20-by-40-foot tents for wstpt library book sale 7/16 - 7/19/2016 install starting 7/9 - wind load bein monitored - inspection tuesday 7/12 a.m.
Work near you
Providers used near 20 Jesup Rd
Showing documented work within 1 mile. Markers are work locations—not provider offices.
This map uses standard image tiles and does not require WebGL.
Open the mapProviders used nearby
0 local providers to explore
Grouped by specialty, with uncategorized work last. Within each specialty, providers are ordered by recent documented work and nearby job count.
Some nearby work records do not identify a provider, and others may still be awaiting a confident property match.
Property facts come from Connecticut’s statewide Parcel and CAMA release. Owner and mailing-address fields are not published here. This page includes work history confidently matched to this address.