27 W La
Ridgefield, CT- 2026Demolition
Total Labor Cost: $64,000Main Tasks:Demolition: Remove entire existing deck structures Footings: Excavate and build 10 footings Concrete Slabs: Build two new slabs for stairs Framing (Various Locations): Extensive framing work on first and second floors including posts, beams, bracing, water shielding, and siding reinstallation (various costs per area ranging Stairs: Build stairsDecking, Trim, Railing, Debris Removal: Install decking, trim posts, install railing sections, and clean up debris, new upper Aztek composite decking with 1/4"gap. 3. TermBegins June 2025, and continues until completion, unless mutually extended. 4. Payment Terms25% advance payment ($16,000) before work begins. Remaining payments due at milestones (within 5 business days of each request). Late payments incur 2% monthly interest.
$64K