8 27 2025
Trumbull, CT- 2025Electrical
Room Remove a failed Marley water tower and Install a new Carrier 30RC-0306620-413.
$18K
Local provider profile
Documented work across Connecticut based on attributed municipal records.
Contact information
These details have not necessarily been claimed or independently confirmed by the provider.
Work history
Individual records are grouped by address. Totals include only values reported in public records and may not equal final construction cost.
Room Remove a failed Marley water tower and Install a new Carrier 30RC-0306620-413.
$18KMove 2 panels 480 volt to new tenant location. From existing 480 volt panel add step down transformer with two 3 phase 208 volt panels with no branch circuit breakers.
$45KRework existing conduits in pool patio area into new locations where grills and mini fridge being located to, re-using 3 existing separate brach circuits, re-feeding 2 ballard light.
$5KELE