Skip to content

Local provider profile

Peter D Diclementi

Documented work across Connecticut based on attributed municipal records.

Reported work volume$4MDocumented jobs
Average project$248KWhere values are reported
First observed2017Available dataset
Categories4Observed work types
Used for work inNorwalk16 jobs

Contact information

Details found in public records

These details have not necessarily been claimed or independently confirmed by the provider.

No contact information was found in the available records.

Work history

Documented work by property

Individual records are grouped by address. Totals include only values reported in public records and may not equal final construction cost.

Satellite view of 10 Norden Pl, Norwalk, CTSatellite view
2025

10 Norden Pl

Norwalk, CT
  • 2025Mechanical

    North East Data Hall Build - out#2- Install PDU's and connect to CDP. Install owner provided RPP panels. Scope includes fire alarm and mechanical (CRAC, HVAC, Humidifiers).

    $601K
  • 2024Mechanical

    North east data hall build out - install PDU's and connect to CDP - load banking, commissioning, testing, install owner provided RPP panels, LED lighting, fire alarm and humidifiers, mechanical scope included.

    $461K
  • 2023Ele Alt Comm

    Southwest Data Hall. Install conduit and feeders for (6) owner-provided RPP panelboards.

    $159K
  • 2023Ele Alt Comm

    Install conduit and feeders for 6 owner-provided RPP panelboards. Install Unistrut 4-by-4-foot stacked grid support for cable tray.

    $265K
  • 2022Electrical

    Data center room 121 east: Install PDU's and connect to CDP, breakers for CRAC's, install a leak detection panel, LED lighting, wire humidifiers, and fire alarm.

    $715K
  • 2022Electrical

    Data Center west, Room 122: Install owner-provided CDP's and PDU's, new feeders, and new fire alarm devices connected to the existing fire alarm control panel.

    $262K
  • 2021Electrical

    Update panelboards, furniture power, lighting and controls, branch wiring, tele/data sleeves, FA connections, and FA devices. Program, start up, and test by FA vendor.

    $63.5K
  • 2021Electrical

    SSB second floor office space - lighting and controls, 100/3 panel, low voltage stubs, conduit and wire for FA, and 2" conduit to data center with pull string.

    $32.1K
  • 2021Electrical

    Lighting and controls, branch, power devices, panelboard work, and low-voltage stubs.

    $29.1K
  • 2021Electrical

    SSB data center expansion: switchgear, panelboards, wiring of PDU's and generator, data cabling, and Unistrut ceiling framing.

    $925K
  • 2021Ele Alt Comm

    State Street Bank (CyrusOne Direct) — install 12 owner-supplied RPPs and pre-made whips.

    $127K
  • 2020Demolition

    Norwalk DR office: demolition, lighting, power devices, panel board work, and fire alarm. B20-1150-Build Alt residence: Install roof-mounted solar panels. E20-1003-Ele No Fee: Install roof-mounted solar panels.

    $172K
  • 2017Electrical

    Electrical - disable exist. system.

    $4K
Satellite view of 2 Tindall Ave, Norwalk, CTSatellite view
2024

2 Tindall Ave

Norwalk, CT
  • 2024Ele Alt Comm

    Phase II—south side: Remove existing light fixtures and conduits to allow for concrete and brick wall repairs. Install new conduit, wire, and boxes. Reinstall existing fixtures.

    $16K
  • 2024Electrical

    Phase I – South side: Remove existing light fixtures and conduits to allow for concrete and brick wall repairs. Install new conduit, wire, and boxes; reinstall existing fixtures.

    $16K
  • 2023Demolition

    Demolish the existing switchgear.

    $126K