49 Summit Rd
Greenwich, CT- 2025Mechanical
HVAC Work
Local provider profile
Documented work across Connecticut based on attributed municipal records.
Contact information
These details have not necessarily been claimed or independently confirmed by the provider.
Work history
Individual records are grouped by address. Totals include only values reported in public records and may not equal final construction cost.
HVAC Work
Install a ductless mini-split for the family room.
$8KHVAC Work
New hydro air handler and AC on the second floor and first floor.
$20KKitchen Renovation. Demolish existing kitchen and relocated to rear of building to existing dining room location. Removal of 2 load bearing walls and installation of structural beams and post. Removal of rear slider at dining room and add window at proposed kitchen sink location. First Floor 1/2 BathAdd shower convert to full bath. Living RoomAdd Electrical high and low voltage for future entertainment built-ins flanking fireplace. Garage Rough in for future sink.
$125KHVAC Work
Run a new exhaust duct for the kitchen hood and install new makeup air for kitchen fresh air.
$2.5KHVAC Work
HVAC Work
HVAC
HVAC
HVAC Work
$13KRelocate 2 returns on third floor: floor two supplies, relocate 4 supplies, supply and install one new air handler and necessary duct work and reconnect 2 existing bath fans, and kitchen exhaust.
$20KRelocate 2 returns 3rd: floor and two supplies, relocate 4 supplies. Supply and install one new hydro air and necc ductwork to accommodate extended master bedroom suite, reconnect 2 existing bath fans/install 1 new bath fan, kitchen exhaust.
$22KIMC; relocate 2 supplies in the renovated bathroom; install 1 new ceiling exhaust fan; relocate 1 supply to the lower level.
Remove and repair existing damaged ductwork per kitchen fire; remove, repair, and re. Install kitchen exhaust duct, bathroom duct, and dryer exhaust duct; start up and test operation of existing equipment.
Reroute 1 return on the first floor. Install kitchen exhaust and 2 bathroom exhaust fans.
Replace 1 gas-fired furnace and one condensing unit; 1 condensing unit, coil, and furnace.
$8.9KComplete installation of one 5-ton split system for the lower-level kitchen area; complete installation of 2 bathroom exhaust fans; complete installation of a duct system for return air rooftop unit; install all registers and grills; test.
Reconnect existing kitchen exhaust. Duct in new location.
Extend the existing duct to supply heating and cooling for the new addition; relocate 2 supplies in the mudroom; reconnect the existing condensing units.
Relocate 4 existing supply registers to accommodate the new kitchen area.
1 nw: hydro and air conditioning new master bedroom; 1 new ductless mini split new theater; supply new ducts and zone for finished third floor. Playroom; relocate 3 returns, first floor., relocate 7 supplies, first floor.; 2 new exhaust. Fans; install kitchen exhaust. And makeup air.
1 hydro a/r handler with air conditioning for lower level and first floor; 1 hydro a/r handler with air conditioning for second floor; kitchen exhaust ducting and bathroom exhaust ducting.
Relocate existing supply to return registers for third floor. Bath; MBR bathroom., WIC, MBR, laundry room, mudroom/laundry room.
Relocate 5 existing supply registers in the renovated mudroom, laundry, bath, and breezeway; 1 dryer exhaust vent; 1 bath for unit; install 1 gas-fired furnace and air conditioning for the existing room above the garage (furnace will be placed in the mechanical room in the garage).
Zone 1 - utilize existing eq. Partial new ductwork; Zone 2: one new Trane Tem6 A/h, and Trane new condenser; Zone 3: utilize existing eq. Partial new ductwork; Zone 4: one new Trane Tem6 A/H, 1 new Trane condenser; all related exhaust. Work, 1 ERV unit.
Replace the existing condensing unit and evaporator coil; place the condenser in a different location from the existing one.
$5KTrane 2-stage gas furnace and air conditioning on the first floor, with 1 zone; Trane 2-stage gas furnace and air conditioning on the second and third floors, with 3 zones and 1 fresh air unit. Exhaust ductwork for bathroom, kitchen, and dryers.
Kitchen exhaust ductwork with makeup air; fresh air supply for existing mechanical space.
1 18000 btu split system for gym area, 1 18000 btu split system for lounge and pr. Ventilation for 1 bathroom. Vent.
Install or relocate 15 new lay-in diffusers and 8 return grilles to the new layout and ceiling plan. Existing equipment and main trunk ducts shall remain. Install a new dehumidifier for the lower level.
Exhaust duct for new bath fan; relocate 1 supply on the second floor in the bedroom. Reconnect 1 existing return register.
Exhaust duct, 1 new bathroom exhaust fan; relocate one existing supply duct in dining room.
Remediation per list provided by others, 9/25/19. Work performed on a time and material basis.
Install 1 ductless mini split unit with 2 wall-mounted cassettes; exhaust duct for kitchen, bathroom, and dryer vent. Amendment (12/7/16): Install ductless heat pump and wall-mounted unit for second space, front apartment; additional hire set for future unit; install condensate lines and rough refrigeration piping for future third-floor apartment.
Install an a/r handler, hydro coil, and condensing unit for a new addition on the second floor. Install 4 supply branches to the lower level for a future air-conditioning-only system on the first floor.
Install 2 new supply registers, new mudroom/ relocate one return; relocate 3 supplies, exhaust. For 1 bathroom., 1 dryer, exist. ea. and design to remain as is.
One Trane gas-fired furnace with air conditioning and 2 zones; one Trane gas-fired furnace with air conditioning and 1 zone.