2 Third St
Norwalk, CT- 2025Electrical
Installing a 3-gang meter/main combination unit: 200 amps for the second-floor apartment, 200 amps for the first-floor apartment, and 100 amps for an owner's meter.
$12K
Local provider profile
Documented work across Connecticut based on attributed municipal records.
Contact information
These details have not necessarily been claimed or independently confirmed by the provider.
Work history
Individual records are grouped by address. Totals include only values reported in public records and may not equal final construction cost.
Installing a 3-gang meter/main combination unit: 200 amps for the second-floor apartment, 200 amps for the first-floor apartment, and 100 amps for an owner's meter.
$12KElectrical Work HVAC
20 devices installed; 1: oven, dishwasher. Existing 200-amp service. Kitchen renovation; relocate 120v stove outlet; relocate 120v hoop; relocate recessed lights and countertop outlet to code; install new 120 v dedicated line for dishwasher in Butler Pantry; relocate Butler Pantry switch locations.
150 devices installed. Refeed the existing cottage at 200-amp There is an existing 400-amp service feeding 4 Alden Rd. Wire the cottage to code with approved plans.
Electrical—about 200 CAT 6 runs to offices, areas, phones, TV, and data.
$20K1: hood vent, rngtp, dshwsh., microwave; install recess lights in living room.; 4 near 20-amp circuits in kitchen; install new closet lt. Location, new microwave outlet, new 20-amp gfi outlet in bathroom.; new bathroom. Shower light; new bedroom. 120 volt smoke det.; new 24 circuit panel with arc fault breakers.
20 Devices; 1 electric heat; rewire existing main foyer, install 6 new recess lights, install 2 new chandeliers locations, 1 chandelier insdie and one exterior wire for 2 new exterior scones locations, step lights for foyer enterance, add 1 zone of floor heat 4800 watts, tie existing light loads and new lightening loads to existing system, add new interior TR outlets as well at 1 exterior GFI outlet.
Upgrade from 100-amp service to 200-amp service; overhead in SEU cable; bonding and grounding as required. 200-amp service.
$1.5K48 kilowatt generator plumbing: Install gas line from the meter to the generator. Receipt 18-2944 for $40 paid.
$18KWire outside for step lights, receptacles, and outside lighting.
100-amp service; GFI receptacles. Amendment (2/25/19): 267 devices installed; 1: rng., oven, clthsdryr, oil burner motor, dishwasher, septic pump, 3: circ. Motors, 2 air conditioning motors, wire for 200-amp service. Amendment (5/7/19): 200-amp service. 200-amp o.h. service work. (Eversource wanted a new work request number for the service, as the old number expired).
1 device installed; 1 car charger; 400-amp service.; existing 320 meter pan to remain; 2 150-amp panels and wiring removed; 2 200-amp panels and wiring installed; 1 Tesla car charger wiring in garage 72-amp 240 volt, clea up wiring at panels.
$12.3K200-amp overhead temporary service for construction of house (I.
$1.2KInstall 200-amp transfer switch; 200-amp disconnect switch; install PVC pipe for a future generator (no generator at this time).
$1.5K400-amp service. Install 400-amp ct/main cabinet; install 2 200-amp panels; check existing wiring, safe off as req'd. Amendment (11/17/17): meter main will now be on pedestal behind carport. Amendment (4/23/18): 400-amp service with 2 200-amp panels; energize and rewire to exterior pump; existing branch circuits will not be energized and are not installed in electrical panels.
$10K12 devices installed; install 4 new 4" recessed lights, a new 100 cfm bath fan, a new GFI, a new vanity light, and a new closet light; relocate camera DUR.
12 devices installed; 1: register, refrig. Remove fluorescent lighting; install track lighting.
8 devices installed; 1 clothes dryer (500 watts); install 120 V line for washer; install 120 V line for gas dryer; install dedicated line for second-floor bath; GFI outlet; relocate second-floor bath switches; install new light fixture in first-floor bath and second-floor bath; install new second-floor bath vent fan.
150 devices installed; 1: rng, dishwasher, clthsdryr, gasbrnr. Motor, jacuzzi, microwave, 2: circ. Motors, air conditioning motors. 200-amp service o.h.; lighting, swtches., receptacles.