540 Hoyt St
Darien, CTOther.
$109KLocal provider profile
Documented work across Connecticut based on attributed municipal records.
Work history
Individual records are grouped by address. Totals include only values reported in public records and may not equal final construction cost.
Other.
$109K94-104 Ursula Place. Construction of a new townhouse with 6 attached units. The building contains 5 2 bedroom units and 1,3 bedroom unit. Total work area 7,032 SF.
$2.7M106-116 Ursula Place: Construct 6 attached townhouse units, comprising five 2-bedroom units and one 3-bedroom unit. Work area: 7,032 SF.
$2.7M118-128 Ursula Place: Construct 6 attached townhouse units, including four 2-bedroom units and two 3-bedroom units. Work area: 7,483 SF.
$2.7MProject consists of 7 townhouse units with a total of 43 unitsThis permit is for Building 2.7138,140,142,144,146,148,150 Ursula place7 units6 two bedroom1 three bedroomincludes 5 Accessible units.
$3.2MOak Park Phase 2 consists of 7 townhouse buildings with a total of 43 units. This permit is for Building 2.2. Addresses 70,72,74,76,76,80 Ursula Place. Seven townhouse units. Five 2 bedroom units and one, 3 bedroom units. Total 7,032 SF gross.
$2.7MFive 2-bedroom units and one 3-bedroom unit.
$2.7MTotal Project - Construction of seven new townhouse buildings. This permit is for Building 2.1 Addresses 58,60,62,64,66 and 68 Ursula PlaceSix units - 5 2 bedroom and 1,3 bedroom.
$2.5MSidewalk Shed.
$10KSidewalk Shed.
$10KConstruction of a new mixed-use, four-story structure with a partial basement, consisting of 39 dwelling units (Use Group R-2), Use Group B administrative offices, a community room, and amenities. Construction type 5A. Total building gross area: 43,924 SF. Certificate of Occupancy subject to Office of the State Building Inspector Modifications M-26-0391, M-26-0246, and M-26-0470.
$14MParking structure and residential above.
$11.2MParking structure and residential above.
$11.2MF/O - Parking garage and residential above – 4 stories.
$2.6M210–220 Ursula Place. New townhouse construction consisting of 6 attached townhouse units: five two-bedroom units and one three-bedroom unit. Total of 7,032 SF. Building 1.3.
$2.2M204-208 Ursula Place: Construct 3 attached 2-bedroom townhouse units. Work area: 3,318 SF.
$1.1M192–202 Ursula Place: 6 attached townhouses with 5 2-bedroom units and 1 3-bedroom unit. Work area: 7,032 SF. 1.1 Building.
$2.2MInstall sidewalk shed.
$4KInstall sidewalk shed.
$4KSelective demo and 155 units, 6 stories and reconstruct.
$23.3MInstall a new 8’ plywood painted fence on Wall Street.
$3KFour attached 2 story town houses containing 4- 2 bedroom units. Total work area 4,428 SFBuilding 1.6.
$1.5MSix attached 2 and 3 story townhouses containing 4 -2 bedroom units and 2-3-bedroom units. Total work area 7,483 SFBuilding 1.7.
$2.2MFour attached 2 and 3 story townhouses with 2-2 bedroom units and 2-, 3 bedroom units. Work area 5,232 SFBuilding 1.5.
$1.5M246-256 Ursula Place (AKA building 1.4) Six attached 2 and 3 story townhouses containing 5 -2 bedroom units and 1-3-bedroom unit. 4 Units # 246,248,254 and 256 are to be Type B units. Total work area 7,032 SF1.4.
$2.2MConstruct a 3-story, 26-unit multifamily building with a total gross floor area of 15,058 SF. Use groups R-2, B, and A-3. Construction type 5B.
$9.6MSuperstructure for a 2-story addition at the rear only.
$908KInterior renovations to an existing two-family house: 1. Tenant unit–basement: New kitchen and new bathroom. 2. Main house–first and second floors: - First floor: New kitchen and bathrooms; remove an existing wall and add a structural beam. Second floor: Renovate the existing bathroom. Replace the exterior deck in kind. Install new windows and new siding.
$175KType 2 interior alteration for future open workspace. Provide new window openings in exterior walls with new storefront windows. Provide a new kitchenette.
$325KType 2 interior alteration for future open workspace. Provide new window openings in exterior walls with new storefront windows. Provide a new kitchenette.
$325KInterior demolition of existing men's and women's room bathrooms, steam rooms, and locker rooms. Demolition of drywall partitions in these rooms. Remove flooring, carpet, and ceramic tile. Remove existing aluminum ceiling.
$35KPlumbing Work
Plumbing Work
Add To & Alter
$8.8MRenovation of 34 units in five buildings and associated sitework. New drywall, flooring, ceilings, windows, PTAC units, kitchens, bathrooms, doors, windows, roofs, and siding. This is phase 4 of the project. 1/30/22. Addition of a natural gas-fired standby generator with an enclosure mounted on a concrete pad. It serves the sump pump in the Building 19 basement. The sump pump is part of the original building permit plans. This generator is emergency backup.
$6.1MSuperstructure for 15 unit residential 3 story building.
$2.8MSuperstructure for 15 unit residential 3 story building.
$2.8MFoundation only for rear 15 unit 3 story building - residential units; P21-0531-plumbing No Fee: New construction - 15 1 bathroom units with washing machine, kitchen, and 40 gallon electric water heater (under slab only); B22-0024-Build New Const Comm: Superstructure for 15 unit residential 3 story building; E22-0220-Ele No Fee: Install new service modular metering 28 total meters with one owners - wire 15 new units per plans, tele/data, fire alarm security and card access by others; P22-0121-plumbing Alt Comm: Design, furnish and install fire protection system; H22-0245-Mech No Fee: HVAC system per plans; P22-0200-plumbing No Fee: Installation of a new six inch PVC sanitary lateral.
$250KDemolish the entire rear building.
$24KExterior restoration and interior remodeling.
$359KCommercial additions and alterations.
$400KFurnish and install DOAS units at Westover Elementary School.
$2.8MFurnish and install DOAS units at Westover Elementary School.
$2.8MAlterations to Westover Elementary School. Phase I: Reduce to core work and site work. Revised 10/28/19 to add Phase II: renovation of school, roof replacement. Reverted 11/18/2019 per MC for liquid propane tank location approval for temporary heat, TM-19-937.
$14.9MBuild a wood deck at Courtyard.
$215KBuild a wood deck at Courtyard.
$215KRepair work after mold remediation.
$10Drywall removal and replacement, HVAC repairs, and electrical work associated with the drywall and HVAC repairs for SAMG. Sitework.
$25KDrywall removal and replacement, HVAC repairs, and electrical work associated with the drywall and HVAC repairs for SAMG. Sitework.
$25KBuild a handicap ramp at the portable classrooms for the Mold Task Force/Stamford Asset Management Group.
$20KRemove the existing retaining wall at the large playground and install a new retaining wall.
$72KRenovations to existing units. Total of 52 units in eight buildings and one building with a management office.
$8.2MBuilding #6, Zone G, fourth floor: Full demolition and renovation of the building interior, including new MEPFP. New exterior façade, including relocation of the exterior wall, windows, roof, siding, and doors. New stair towers for egress. Site improvements. State education fee paid: $1,152.84. Electrical: NEC, 18-unit apartment building; new 600-amp service; 240 switches, 300 outlets, and 240 light fixtures. Plumbing: First floor: 4 water closets, tubs, and sinks; Basement: 3 clothes washers; Second floor: 4 water closets, tubs, and sinks; Third floor: 5 water closets, tubs, and sinks; Fourth floor: 5 water closets, tubs, and sinks.
$4.4MBuilding #6, Zone G, fourth floor: Full demolition and renovation of the building interior, including new MEPFP. New exterior façade, including relocation of the exterior wall, windows, roof, siding, and doors. New stair towers for egress. Site improvements. State education fee paid: $1,152.84. Electrical: NEC, 18-unit apartment building; new 600-amp service; 240 switches, 300 outlets, and 240 light fixtures. Plumbing: First floor: 4 water closets, tubs, and sinks; Basement: 3 clothes washers; Second floor: 4 water closets, tubs, and sinks; Third floor: 5 water closets, tubs, and sinks; Fourth floor: 5 water closets, tubs, and sinks.
$4.4MBuilding #6, Zone J, attic: Full demolition and renovation of the building interior, including new MEPFP. New exterior façade, including relocation of the exterior wall, windows, roof, siding, and doors. New stair towers for egress. Site improvements. State education fee paid: $1,152.84. Electrical: NEC, 18-unit apartment building; new 600-amp service; 240 switches, 300 outlets, and 240 light fixtures. Plumbing: First floor: 4 water closets, tubs, and sinks; Basement: 3 clothes washers; Second floor: 4 water closets, tubs, and sinks; Third floor: 5 water closets, tubs, and sinks; Fourth floor: 5 water closets, tubs, and sinks.
$4.4MBuilding # 6 - ZONE A - FIRST FLOOR - Full demo and renovation of building interior including new MEPFP. New exterior fascade including relocaiton of ext. Wall, windows, roof, siding and doors. New Stair towers for egress. Site improvements, State ed fee paid $1152.84 electrical: NEC 18 unit apartment building; new 600-amp service. 240 switches, 300 outlets, and 240 light fixtures. PLUMB: First floor: 4 water closets, tubs, sinks, basement: 3: clthswhsrs., Second floor: 4 water closets, tubs, sink, Third floor: 5 water closets, tubs, sinks; fourth floor.: 5 water closets, tubs, sinks.
$4.4MBuilding #6, Zone B, first floor: Full demolition and renovation of the building interior, including new MEPFP. New exterior facade, including relocation of the exterior wall, windows, roof, siding, and doors. New stair towers for egress. Site improvements. State education fee paid: $1,152.84. Electrical: NEC, 18-unit apartment building; new 600-amp service; 240 switches, 300 outlets, and 240 light fixtures. Plumbing: First floor: 4 water closets, tubs, and sinks; Basement: 3 clothes washers; Second floor: 4 water closets, tubs, and sinks; Third floor: 5 water closets, tubs, and sinks; Fourth floor: 5 water closets, tubs, and sinks.
$4.4MBuilding #6, Zone D, second floor: Full demolition and renovation of the building interior, including new MEPFP. New exterior façade, including relocation of the exterior wall, windows, roof, siding, and doors. New stair towers for egress. Site improvements. State education fee paid: $1,152.84. Electrical: NEC, 18-unit apartment building; new 600-amp service; 240 switches, 300 outlets, and 240 light fixtures. Plumbing: First floor: 4 water closets, tubs, and sinks; Basement: 3 clothes washers; Second floor: 4 water closets, tubs, and sinks; Third floor: 5 water closets, tubs, and sinks; Fourth floor: 5 water closets, tubs, and sinks.
$4.4MBuilding #6, Zone C, second floor: Full demolition and renovation of the building interior, including new MEPFP. New exterior facade, including relocation of the exterior wall, windows, roof, siding, and doors. New stair towers for egress. Site improvements. State education fee paid: $1152.84. Electrical: NEC, 18-unit apartment building; new 600-amp service; 240 switches, 300 outlets, and 240 light fixtures. Plumbing: First floor: 4 water closets, tubs, and sinks; Basement: 3 clothes washers; Second floor: 4 water closets, tubs, and sinks; Third floor: 5 water closets, tubs, and sinks; Fourth floor: 5 water closets, tubs, and sinks.
$4.4MBuilding #6: Full demolition and renovation of the building interior, including new MEPFP. New exterior façade, including relocation of the exterior wall, windows, roof, siding, and doors. New stair towers for egress. Site improvements. State education fee paid: $1,152.84. HVAC: IEBC–building #6; IMC. Exhaust fans and all necessary ductwork and hydronic piping per plans and specifications. Electrical: NEC. 18-unit apartment building; new 600-amp service. 240 switches, 300 outlets, and 240 light fixtures. Plumbing: First floor: 4 water closets, tubs, and sinks; Basement: 3 clothes washers; Second floor: 4 water closets, tubs, and sinks; Third floor: 5 water closets, tubs, and sinks; Fourth floor: 5 water closets, tubs, and sinks. Plumbing (2): IEBC–building #6; install new fire sprinkler system per NFPA 13R.
$4.4MBuilding #6, Zone I, attic: Full demolition and renovation of the building interior, including new MEPFP. New exterior façade, including relocation of the exterior wall, windows, roof, siding, and doors. New stair towers for egress. Site improvements. State education fee paid: $1,152.84. Electrical: NEC, 18-unit apartment building; new 600-amp service, 240 switches, 300 outlets, and 240 light fixtures. Plumbing: First floor: 4 water closets, tubs, and sinks; Basement: 3 clothes washers; Second floor: 4 water closets, tubs, and sinks; Third floor: 5 water closets, tubs, and sinks; Fourth floor: 5 water closets, tubs, and sinks.
$4.4MBuilding #6, Zone E, third floor: Full demolition and renovation of the building interior, including new MEPFP. New exterior facade, including relocation of the exterior wall, windows, roof, siding, and doors. New stair towers for egress. Site improvements. State education fee paid: $1,152.84. Electrical: NEC, 18-unit apartment building; new 600-amp service; 240 switches, 300 outlets, and 240 light fixtures. Plumbing: First floor: 4 water closets, tubs, and sinks; Basement: 3 clothes washers; Second floor: 4 water closets, tubs, and sinks; Third floor: 5 water closets, tubs, and sinks; Fourth floor: 5 water closets, tubs, and sinks.
$4.4MBuilding #6, Zone F, third floor: Full demolition and renovation of the building interior, including new MEPFP. New exterior façade, including relocation of the exterior wall, windows, roof, siding, and doors. New stair towers for egress. Site improvements. State education fee paid: $1,152.84. Electrical: NEC, 18-unit apartment building; new 600-amp service; 240 switches, 300 outlets, and 240 light fixtures. Plumbing: First floor: 4 water closets, tubs, and sinks; Basement: 3 clothes washers; Second floor: 4 water closets, tubs, and sinks; Third floor: 5 water closets, tubs, and sinks; Fourth floor: 5 water closets, tubs, and sinks.
$4.4MBuilding #6, Zone J, attic. Full demolition and renovation of the building interior, including new MEPFP. New exterior façade, including relocation of the exterior wall, windows, roof, siding, and doors. New stair towers for egress. Site improvements. State education fee paid: $1,152.84. Electrical: NEC, 18-unit apartment building; new 600-amp service; 240 switches, 300 outlets, and 240 light fixtures. Plumbing: First floor: 4 water closets, tubs, and sinks; Basement: 3 clothes washers; Second floor: 4 water closets, tubs, and sinks; Third floor: 5 water closets, tubs, and sinks; Fourth floor: 5 water closets, tubs, and sinks.
$4.4MInternational Existing Building Code (IEBC) – Building #6, Zone H, fourth floor: Full demolition and renovation of the building interior, including new mechanical, electrical, plumbing, and fire protection (MEPFP). New exterior façade, including relocation of the exterior wall, windows, roof, siding, and doors. New stair towers for egress. Site improvements. State education fee paid: $1,152.84. Electrical: National Electrical Code (NEC), 18-unit apartment building; new 600-amp service, 240 switches, 300 outlets, and 240 light fixtures. Plumbing: First floor: 4 water closets, tubs, and sinks; Basement: 3 clothes washers; Second floor: 4 water closets, tubs, and sinks; Third floor: 5 water closets, tubs, and sinks; Fourth floor: 5 water closets, tubs, and sinks.
$4.4MBuilding #3 - ZONE A - FIRST FLOOR - Full demo and renovation of building interior incude new MEPFP. New Ext. Facade including relocation of ext. Wall, windows, roof, siding and doors. New stair towers for egress. Site Improvements. State ed fee paid $700.44 electrical: NEC. 100-amp temp. service and trailer connection 100-amp service. Amendment (4/6/21): NEC. 12 Unit Apartment Building. New 400-amp service 140 switches, 200 outlets, and 160 light fixtures. PLUMB: Second floor: 4 water closets, tubs, sink, Third floor: 5 water closets, tubs, sinks; fourth floor.: 5 water closets, tubs, sinks; new plumb. For 12 units; 10 1 bathroom units, and 2, 2 bathroom units.
$2.7MBuilding #3 - ZONE A - FIRST FLOOR - Full demo and renovation of building interior incude new MEPFP. New Ext. Facade including relocation of ext. Wall, windows, roof, siding and doors. New stair towers for egress. Site Improvements. State ed fee paid $700.44 electrical: NEC. 100-amp temp. service and trailer connection 100-amp service. Amendment (4/6/21): NEC. 12 Unit Apartment Building. New 400-amp service 140 switches, 200 outlets, and 160 light fixtures. PLUMB: Second floor: 4 water closets, tubs, sink, Third floor: 5 water closets, tubs, sinks; fourth floor.: 5 water closets, tubs, sinks; new plumb. For 12 units; 10 1 bathroom units, and 2, 2 bathroom units.
$2.7MBuilding #3 - ZONE D - ATTIC - Full demo and renovation of building interior incude new MEPFP. New Ext. Facade including relocation of ext. Wall, windows, roof, siding and doors. New stair towers for egress. Site Improvements. State ed fee paid $700.44 electrical: NEC. 100-amp temp. service and trailer connection 100-amp service. Amendment (4/6/21): NEC. 12 Unit Apartment Building. New 400-amp service 140 switches, 200 outlets, and 160 light fixtures. PLUMB: Second floor: 4 water closets, tubs, sink, Third floor: 5 water closets, tubs, sinks; fourth floor.: 5 water closets, tubs, sinks; new plumb. For 12 units; 10 1 bathroom units, and 2, 2 bathroom units.
$2.7MBuilding #3 - ZONE C - THIRD FLOOR - Full demo and renovation of building interior incude new MEPFP. New Ext. Facade including relocation of ext. Wall, windows, roof, siding and doors. New stair towers for egress. Site Improvements. State ed fee paid $700.44 electrical: NEC. 100-amp temp. service and trailer connection 100-amp service. Amendment (4/6/21): NEC. 12 Unit Apartment Building. New 400-amp service 140 switches, 200 outlets, and 160 light fixtures. PLUMB: Second floor: 4 water closets, tubs, sink, Third floor: 5 water closets, tubs, sinks; fourth floor.: 5 water closets, tubs, sinks; new plumb. For 12 units; 10 1 bathroom units, and 2, 2 bathroom units.
$2.7MBuilding #3 - ZONE B - SECOND FLOOR - Full demo and renovation of building interior incude new MEPFP. New Ext. Facade including relocation of ext. Wall, windows, roof, siding and doors. New stair towers for egress. Site Improvements. State ed fee paid $700.44 electrical: NEC. 100-amp temp. service and trailer connection 100-amp service. Amendment (4/6/21): NEC. 12 Unit Apartment Building. New 400-amp service 140 switches, 200 outlets, and 160 light fixtures. PLUMB: Second floor: 4 water closets, tubs, sink, Third floor: 5 water closets, tubs, sinks; fourth floor.: 5 water closets, tubs, sinks; new plumb. For 12 units; 10 1 bathroom units, and 2, 2 bathroom units.
$2.7MBuilding #3 -Full demo and renovation of building interior incude new MEPFP. New Ext. Facade including relocation of ext. Wall, windows, roof, siding and doors. New stair towers for egress. Site Improvements. State ed fee paid $700.44 electrical: NEC. 100-amp temp. service and trailer connection 100-amp service. Amendment (4/6/21): NEC. 12 Unit Apartment Building. New 400-amp service 140 switches, 200 outlets, and 160 light fixtures. PLUMB: Second floor: 4 water closets, tubs, sink, Third floor: 5 water closets, tubs, sinks; fourth floor.: 5 water closets, tubs, sinks; new plumb. For 12 units; 10 1 bathroom units, and 2, 2 bathroom units PLUMB (2): install new fire sprinkler system per HFPA 13R.
$2.7MBuilding #1, Zone D, fourth floor: Full demolition and renovation of the building interior, including new MEPFP. New exterior façade, including relocation of the exterior wall, windows, roof, siding, and doors. New stair towers for egress. Site improvements. State education fee paid: $929.76. Electrical: NEC, 200-amp temporary service. Amendment (4/5/21): NEC. 12-unit apartment building. New 600-amp service; 140 switches, 200 outlets, and 160 light fixtures. Plumbing: First floor: 2 water closets, floor drain, 3 clthswshrs.; Second floor: 4 water closets, tubs, sinks; Third floor: 4 water closets, sinks, tubs; Fourth floor: 4 water closets, tubs, sinks.
$3.6MBuilding #1, Zone D, fourth floor: Full demolition and renovation of the building interior, including new MEPFP. New exterior façade, including relocation of the exterior wall, windows, roof, siding, and doors. New stair towers for egress. Site improvements. State education fee paid: $929.76. Electrical: NEC, 200-amp temporary service. Amendment (4/5/21): NEC. 12-unit apartment building. New 600-amp service; 140 switches, 200 outlets, and 160 light fixtures. Plumbing: First floor: 2 water closets, floor drain, 3 clthswshrs.; Second floor: 4 water closets, tubs, sinks; Third floor: 4 water closets, sinks, tubs; Fourth floor: 4 water closets, tubs, sinks.
$3.6MBuilding #1: Full demolition and renovation of the building interior, including new MEPFP. New exterior façade, including relocation of the exterior wall, windows, roof, siding, and doors. New stair towers for egress. Site improvements. State education fee paid: $929.76. Electrical: NEC, 200-amp temporary service. Amendment (4/5/21): NEC, 12-unit apartment building; new 600-amp service, 140 switches, 200 outlets, and 160 light fixtures. Plumbing: First floor: 2 water closets, floor drain, and 3 clothes washers. Second floor: 4 water closets, tubs, and sinks. Third floor: 4 water closets, sinks, and tubs. Fourth floor: 4 water closets, tubs, and sinks. Plumbing (2): IEBC–building #1: Install new fire sprinkler system per NFPA 13 R.
$3.6MBuilding #1 - ZONE A - FRIST FLOOR - Full demo and renovation of building interior including new MEPFP. New Ext. Fascade including relocaiton of ext. Wall, windows, roof, siding and doors. New stair towers for egress. Site improvements. State ed fee paid $929.76 electrical: NEC. 200-amp temp. service. Amendment (4/5/21): NEC. 12 unit apartment building. New 600-amp service 140 switches, 200 outlets, and 160 light fixtures PLUMB: first floor.: 2 water closets, floor-drn., 3: clthswshrs.; Second floor: 4 water closets, tubs, sinks; third floor.: 4 water closets, sinks, tubs; fourth floor.: 4 water closets, tubs, sinks.
$3.6MBuilding #1, Zone C, third floor: Full demolition and renovation of the building interior, including new MEPFP. New exterior facade, including relocation of the exterior wall, windows, roof, siding, and doors. New stair towers for egress. Site improvements. State education fee paid: $929.76. Electrical: NEC, 200-amp temporary service. Amendment (4/5/21): NEC. 12-unit apartment building. New 600-amp service, 140 switches, 200 outlets, and 160 light fixtures. Plumbing: First floor: 2 water closets, floor drain, 3 clothes washers; Second floor: 4 water closets, tubs, sinks; Third floor: 4 water closets, sinks, tubs; Fourth floor: 4 water closets, tubs, sinks.
$3.6MBuilding #1, Zone B, second floor: Full demolition and renovation of the building interior, including new MEPFP. New exterior façade, including relocation of the exterior wall, windows, roof, siding, and doors. New stair towers for egress. Site improvements. State education fee paid: $929.76. Electrical: NEC, 200-amp temporary service. Amendment (4/5/21): NEC, 12-unit apartment building. New 600-amp service; 140 switches, 200 outlets, and 160 light fixtures. Plumbing: First floor: 2 water closets, floor drain, 3 clothes washers. Second floor: 4 water closets, tubs, sinks. Third floor: 4 water closets, sinks, tubs. Fourth floor: 4 water closets, tubs, sinks.
$3.6MBuilding #1, Zone E, attic: Full demolition and renovation of the building interior, including new MEPFP. New exterior façade, including relocation of the exterior wall, windows, roof, siding, and doors. New stair towers for egress. Site improvements. State education fee paid: $929.76. Electrical: NEC, 200-amp temporary service. Amendment (4/5/21): NEC, 12-unit apartment building. New 600-amp service, 140 switches, 200 outlets, and 160 light fixtures. Plumbing: First floor: 2 water closets, floor drain, 3 clothes washers; Second floor: 4 water closets, tubs, sinks; Third floor: 4 water closets, sinks, tubs; Fourth floor: 4 water closets, tubs, sinks.
$3.6MMiscellaneous mold remediation and roof repair work for the City of Stamford Asset Management Group/Mold Task Force. Stamford Asset Management work–annual permit per 2015 IBC 105.1.1. Fees will be paid at close-out. 11 21 2019.
Stamford asset management work – annual permit per 2015 IBC 105.1.1.
$100KUpgrades to Rippowam Manor, a total of 81 units. Miscellaneous upgrades in common areas. New emergency generator and miscellaneous sitework.
$4.7MWork at Stamford High School as authorized by City of Stamford Asset Management Group.
$70KRenovate the existing storage room. Add HVAC, relocate existing sprinklers, and install ceiling tile, flooring, and electrical work.
$100KRenovate the existing storage room. Add HVAC, relocate existing sprinklers, and install ceiling tile, flooring, and electrical work.
$100KRepair work after mold remediation. Made inactive; contractor will not be doing any work.
$10Renovations to exist. 4 unit building. And add 3 sty. 15 unit residence with parking below.
$2.8MRenovations to exist. 4 unit building. And add 3 sty. 15 unit residence with parking below.
$2.8MDemolition of the detached garage and rear addition on the main building.
$20KDemolition of interior walls.
$10KRepair work after mold remediation. Made inactive; the contractor will not be doing any work.
$10Repair work after mold remediation.
$10Interior demolition of the first floor.
$15KRebuild/ repair 54 unit fire damaged condo.
$6.7MZone 18 – Site work, electrical underground. Add 4 stories to the existing building, with a 24,500 sf building connected to the existing building by a bridge. State education fee paid: $1,092. Underground plumbing only for apartment units. Amendment (8/26/15): First floor: 5 water closets, showers, and sinks; Second floor: 7 water closets, showers, and sinks; Third floor: 6 water closets, showers, and sinks; Fourth floor: 7 water closets, a shower, and sinks; 2 clothes washers. Gas pipe from the existing building; new 25-unit apartments. Plumbing (2): Install fire sprinklers in the new addition. Prints in file BB. Electrical: Underground conduit; install temporary power from the existing electrical service. 100-amp 30 om. Underground work only.
$4.2MZone 18 – Site work, electrical underground. Add 4 stories to the existing building, with a 24,500 sf building connected to the existing building by a bridge. State education fee paid: $1,092. Underground plumbing only for apartment units. Amendment (8/26/15): First floor: 5 water closets, showers, and sinks; Second floor: 7 water closets, showers, and sinks; Third floor: 6 water closets, showers, and sinks; Fourth floor: 7 water closets, a shower, and sinks; 2 clothes washers. Gas pipe from the existing building; new 25-unit apartments. Plumbing (2): Install fire sprinklers in the new addition. Prints in file BB. Electrical: Underground conduit; install temporary power from the existing electrical service. 100-amp 30 om. Underground work only.
$4.2MZONE 17 - Frist Floor Existing Building - Add 4 stories(to exising building), 24,500 sf building connected to existing building by a bridge. State ed fee paid $1092. PLUMB: UNDERGROUND PLUMBING ONLY for Apt. Units. Amendment (8/26/15): First floor: 5 water closets, showers, sinks, Second floor: 7 water closets, showers, sinks, Third floor: 6 water closets, showers, sinks; Fourth floor: 7 water closets, shower, sinks, 2: clthswshrs.; gas pipe from existing building.; new 25 unit apts. PLUMB (2): install fire sprinklers in new addition. Prints in file BB. Electrical: underground conduit; install temp. power from existing electrical. Service 100-amp 30 om. Underground work only.
$4.2MZone 19. Site work: underground electrical work for parking lot lighting. Add 4 stories to the existing building; 24,500 sf building connected to the existing building by a bridge. State education fee paid: $1092. Underground plumbing only for apartment units. Amendment (8/26/15): First floor: 5 water closets, showers, and sinks; Second floor: 7 water closets, showers, and sinks; Third floor: 6 water closets, showers, and sinks; Fourth floor: 7 water closets, a shower, and sinks, and 2 clothes washers. Gas pipe from the existing building. New 25-unit apartments. Plumbing (2): install fire sprinklers in the new addition. Prints in file BB. Electrical: underground conduit; install temporary power from existing electrical service. 100-amp 30 om. Underground work only.
$4.2MZone 20 – Site work, underground electrical, and sewer pump. Add 4 stories to the existing building; 24,500 sf building connected to the existing building by a bridge. State education fee paid: $1092. Plumbing: Underground plumbing only for apartment units. Amendment (8/26/15): First floor: 5 water closets, showers, and sinks; Second floor: 7 water closets, showers, and sinks; Third floor: 6 water closets, showers, and sinks; Fourth floor: 7 water closets, showers, and sinks, and 2 clothes washers. Gas pipe from existing building. New 25-unit apartments. Plumbing (2): Install fire sprinklers in new addition. Prints in file BB. Electrical: Underground conduit; install temporary power from existing electrical service. 100-amp 30 om. Underground work only.
$4.2M