Zone 3 – third floor – Sessions Clinic. Revisions to third-floor tenant space. Greenwich Hospital state education fee paid: $93.60.
$360K2019Renovation
Lessee: Greenwich Hospital tenant buildout for Greenwich Hospital on the first and second floors. State education fee paid: $195.00.
$750K2019BU2 ALT INST
Zone 2, third floor, Nuclear Medicine. Revisions to the third-floor tenant space. Greenwich Hospital state education fee paid: $93.60.
$360K2019BU2 ALT INST
Zone 2 – third floor – Nuclear Medicine. Revisions to the third-floor tenant space. Greenwich Hospital state education fee paid: $93.60.
$360K2019Renovation
Revisions to third-floor tenant space. Greenwich Hospital state education fee paid: $93.60.
$360K2019BU2 ALT INST
Zone 1 – #rd floor – Heart and Vascular Clinic. Revisions to third-floor tenant space. Greenwich Hospital state education fee paid: $93.60.
$360K2016Mechanical
Zone 2. Third-floor exterior façade renovations. State education fee paid: $169.00. Amendment #1 (6.14.17): Value $180,000; fee $2,786.80. Elevator addition, approximately 600 SF. Amendment #2 (11.8.17): Value $2,000,000; fee $30,589. Interior tenant fit-out and related work for Greenwich Hospital tenant. Amendment #3 (5.22.18): Fee $100. Revision to third-floor interior tenant HVAC. Core building mechanical upgrades consisting of 1 new chiller, 3 air handling units, 4 boilers, 4 condensing units, pumps, hot water coils, fans, and controls. Tenant fit-out work consists of new PTACs, VAV boxes, radiators, and split systems per plans and specifications. Plumbing: Second floor: 7 new water closets, basins, 24 new sinks, and 1 new floor drain. Third floor: 13 new water closets, basins, 47 new sinks, and 2 new showers. Install gas piping from meter to boilers; install new water, waste, and vent piping to serve the new fixture layout; install water heaters and plumbing fixtures; install medical gas piping and outlets. Plumbing (2): Modify the existing fire sprinkler system at Greenwich Hospital Outpatient Facility. Electrical: 319 devices installed on the second and third floors; install low-voltage plenum cable for phones and computers. Lessee: Greenwich Hospital Assn. Electrical wiring for equipment, lighting, and power to accommodate the tenants’ needs, per plans and specifications submitted and on file. Electrical (2): Install temperature controls for HVAC equipment serving the second and third floors; install thermostats. Electrical (3): CCTV system on the second and third floors; install access control system on the second and third floors.
$650K2016Mechanical
ZONE 3 - Elevator, Atrium and Breezeway - Exterior facade renovations. State Ed. Fee paid.: $169.00 Amend #1: 6.14.17 val $180,000 fee $2,786.80 elevator addition +/- 600 SF Amend #2: 11.8.17 val $2,000,000 fee $30,589 interior tenant fitout and related work for Greenwich Hospital tenant Amend #3: 5.22.18 fee $100 revision to third floor interior tenant HVAC: core building mechanical upgrades consisting of 1: new chiller, 3: a/r hndling units, 4 boilers, 4 condensing units, pumps, hot water coils, fans and controls; tenant fitout work consistang of new PTACS, vav boxes, rads, and split systems per plans and specs. PLUMB: Second floor: 7 nw: water closets, basins, 24 nw sinks, 1 nw: floor-drn.; Third floor: 13 nw: water closets, basins, 47 nw: sinks, 2 nw: showers.install gas piping from meter to boilers; install new water, waste and ventpiping to serve new fixture layout; water heaters and plumbing fixtures; install medical gas piping and outlets PLUMB (2): modify existing fire sprinkler system at Greenwich Hospital Outpatient Facility electrical: 319 devices installed; 2nd and 3rd floors., install low voltage plenum cable for phones and computers Lessee: Greenwich Hospital Assn.; electrical wiring of equipment, lighting and power accommodating the tenants' needs as per plans and specs submitted and on file electrical (2): install temperature controls for hvac equipment serving second and third floor.; install thermostats electrical (3): cctv system, 2nd and 3rd floors.; install access control system 2nd and 3rd floors.
$650K2016Renovation
Exterior facade renovations. State education fee paid: $169.00. Amendment #1: 6.14.17, value $180,000, fee $2,786.80; elevator addition, approximately 600 SF. Amendment #2: 11.8.17, value $2,000,000, fee $30,589; interior tenant fitout and related work for Greenwich Hospital tenant. Amendment #3: 5.22.18, fee $100; revision to third-floor interior tenant.
$650K2016Mechanical
Zone 1. Second-floor exterior façade renovations. State education fee paid: $169.00. Amendment #1 (6.14.17): Value $180,000; fee $2,786.80. Elevator addition, approximately 600 SF. Amendment #2 (11.8.17): Value $2,000,000; fee $30,589. Interior tenant fit-out and related work for Greenwich Hospital tenant. Amendment #3 (5.22.18): Fee $100. Revision to third-floor interior tenant work. HVAC: Core building mechanical upgrades consisting of 1 new chiller, 3 air handling units, 4 boilers, 4 condensing units, pumps, hot water coils, fans, and controls. Tenant fit-out work consists of new PTACS, VAV boxes, radiators, and split systems per plans and specifications. Plumbing, Second floor: 7 new water closets, basins, 24 new sinks, and 1 new floor drain. Third floor: 13 new water closets, basins, 47 new sinks, and 2 new showers. Install gas piping from meter to boilers; new water, waste, and vent piping to serve the new fixture layout; water heaters and plumbing fixtures; and medical gas piping and outlets. Plumbing (2): Modify existing fire sprinkler system at Greenwich Hospital Outpatient Facility. Electrical: 319 devices installed on the second and third floors. Install low-voltage plenum cable for phones and computers. Lessee: Greenwich Hospital Assn. Electrical wiring for equipment, lighting, and power to accommodate the tenants' needs, per plans and specifications submitted and on file. Electrical (2): Install temperature controls for HVAC equipment serving the second and third floors; install thermostats. Electrical (3): CCTV system on the second and third floors; install access control system on the second and third floors.